Case Study: Asbestos Removal for Major Construction Company in Warrington 

Location: Warrington           Services Used: Asbestos Removal

Get In Touch

Removing over 200 tonnes of asbestos for a North West construction firm

BLS Asbestos Limited was contracted by one of their existing clients, a major UK Construction company securing new business in the North West. The scheme has been driven forward by Warrington Borough Council and development companies for completion in 2019.

When fully completed the development will provide 400 new permanent jobs in the leisure, retail and restaurant sectors.

The works consisted of

BLS Asbestos Limited removing and disposing of asbestos containing materials to numerous individual premises. The works spanned 10 weeks and included the removal and disposal of:

AIB panels to high level external soffits

Artex to internal plasterboard bulkheads and beam cladding

AIB ceiling panels

Asbestos floor screed

Galbestos cladding to external fascias

Floor tiles and bitumen adhesive

AIB door beading and transom panels

Cement roof tiles and internal ceiling panels

Contaminated rubble

Overall, approximately 221 tonnes of asbestos waste was removed and disposed of during this project.

Project Management and Safety Controls

ASB5 and ASBNNLW1 notifications were prepared and issued to the HSE for each site location. All work areas were segregated from other site personnel using physical barriers and asbestos enclosures, which were maintained under negative pressure throughout the works.

In addition to the inherent asbestos risks, several non-asbestos hazards were identified, including work at height, manual handling, hand–arm vibration, live mechanical and electrical services, and nearby demolition activities. Each risk was carefully assessed and mitigated by means of site-specific risk assessments, with suitable method statements prepared for every work location.

A UKAS-accredited analytical consultancy was appointed to carry out independent clearances of all work areas and issue certificates of reoccupation to the client, enabling demolition works to proceed safely.

Despite additional ACMs being identified during demolition, BLS successfully increased labour resources and completed the works within the agreed programme.

Other Case Studies

Asbestos Removal for David Brown Gears in Huddersfield

BLS Asbestos successfully completed the removal of asbestos-containing materials at the David Brown Gears manufacturing site in Huddersfield to facilitate the refurbishment for a new wind turbine gear facility.

Asbestos Removal at Grade 1 Listed Building in West Yorkshire

BLS Asbestos Ltd successfully removed asbestos from the light wells of a Grade I listed building in West Yorkshire, enabling its renovation for future use while ensuring compliance with safety regulations.

Asbestos Removal from Hopwood Hall College, Rochdale

The case study details the successful asbestos removal project at Hopwood Hall College in Rochdale, which was essential for repairing flood-damaged areas and ensuring the safe reopening of the college's IT and childcare departments.

Asbestos Removal from Leeds City College’s Technology Campus

BLS Asbestos Ltd successfully completed the removal of asbestos from the basement of Leeds City College's Technology Campus on a tight deadline, ensuring minimal disruption to the college's operations.

Asbestos Removal at Leeds Demolition Site

BLS Asbestos successfully removed and disposed of various asbestos-containing materials from a disused property in Leeds, ensuring the site was safe for demolition and future regeneration.

Asbestos Removal at Leeds Junior School

BLS Asbestos successfully removed asbestos insulating board from Yeadon Westfield Junior School's caretaker's residence to facilitate the construction of a new classroom, ensuring safety during the process by scheduling the work over the Easter break.

Asbestos Removal at Major Construction Company in Warrington

BLS Asbestos Limited successfully removed and disposed of over 221 tonnes of asbestos from multiple premises for a major construction company in Warrington, contributing to a development project that will create 400 new jobs in the region.

Asbestos Removal from Nestle’s Halifax Site

The case study details the successful removal of asbestos from Nestle's Halifax office building to facilitate a security relocation project, emphasizing health and safety throughout the process.

Asbestos Removal for the Reserve Forces’ and Cadets’ Association

BLS Asbestos Ltd successfully removed asbestos-containing materials from the boiler room of the Territorial Army Centre in Scunthorpe, ensuring safe operations for maintenance.

Asbestos Removal for Southampton Retail Fit-Out

BLS Asbestos was instructed by Sports Direct to remove all asbestos containing materials from a former BHS site in Southampton.

Asbestos Removal from The Old Vinyl Factory in Hayes

BLS Asbestos was commissioned to remove asbestos containing pipe insulation from the sub-floor ducts within the Old Vinyl Factory.

Asbestos Removal Contract for West Yorkshire School

BLS Asbestos undertook asbestos removal work in the riser, boiler room and undercroft area of a West Yorkshire High School.